| Inner city charter update |
|
|
|
| Written by Neil Fraser | |
| Monday, 10 March 2008 | |
|
The Inner City Charter Partnership Forum has held its second meeting, and has reported that a fair amount of work is under way in the inner city.
Neil Fraser
I AM back from cold London, but unfortunately returned a day late for the second meeting of the Inner City Charter Partnership Forum, which was held on Tuesday, 4 March at the World of Beer Conference Centre in Newtown. However, Yael Horowitz, the inner city programme manager, kindly forwarded me the information that was made available at the meeting, enabling me to provide the following update.
Background * The Inner City Regeneration Charter reflects the work of the stakeholder working groups, which held workshops with stakeholders and interested parties in the run-up to the summit, and is thus divided into six clusters:
* The City of Johannesburg recommitted to and re-elevated inner city initiatives and publicly made a specific "ring-fenced" budget available for the plans:
* The Charter was formally approved by the mayoral committee on 19 July 2007. * The Inner City Partnership Forum was launched on 7 November 2007.
Charter vision
Regardless of the functions and people it accommodates, in future the Johannesburg inner city will be well managed, safe and clean. It will not be a dormitory for the poor, nor an exclusive enclave of loft apartments, galleries and coffee shops.
Urban management, safety and security
Summary of progress * Inner city broken into four quadrants and quadrant teams in place; * Dedicated capacity from various departments now contributes 136 enforcement officials and 30 urban inspectors have been hired; * Systematic response, with zone-by-zone, block-by-block interventions beginning to show positive results; * Emphasis on empirical information and early warning systems via geoinformation systems, call centre tracking and enhanced monitoring. The gaps and needs are now readily identifiable - the challenge is to get municipal-owned entities to respond effectively; * Coherent programme of support for city improvement districts and three RIDs ready for the mayoral committee; * Eight one-day public education campaigns already conducted. By-law education material has been designed for a major education campaign to roll out over next few months; * Initial work on an integrated database of bad buildings (owners and directors of companies, cut-offs, amount owing and so on) completed. Being further developed along with other strategies; * Commitment to have 216 CCTV cameras up and running by June 2008 (doubling of network) is ahead of schedule. Four dedicated response vehicles and staff have been agreed; and * Imperative that capital spend is supported by public and private management initiatives.
Public spaces
Summary of progress * Necessary to allocate further capital funding to Hillbrow, Berea and Yeoville in the 2008- 09 financial year to complete some initiatives; * Approximately R127-million of the R300-million is in the process of being awarded. After community consultation, the Johannesburg Development Agency on site as from January with five contractors; and * Focus on iconic public spaces will happen concurrent with the development of the Spatial Development Framework and Regional Spatial Development Framework review.
Arts, culture and heritage
Summary of progress * Development of mechanisms to ensure proper and sustainable financing, organisation, marketing and management of all events - liaising with the Gauteng provincial government in this regard as the City of Johannesburg cannot undertake it alone; * Clear public art programme in tandem with redevelopment of the public realm - on track in Hillbrow, Berea and Yeoville and consultants have been appointed; * Web-based information sharing portal being investigated; * Access audit to all city venues has been undertaken - the issue remains the capital needed to ensure compliance and ongoing maintenance; and * All heritage plans ready for roll-out should the budget become available.
Economic development
Summary of progress * Roll out of smart card system has been delayed, now working with Johannesburg Inner City Business Coalition (JICBC) to expedite; * Hoek Street partnership market delayed, progress now being made; * RFP for appointment of consultant project team to design further linear markets currently out to tender; * Major institutional and management issues with Metro Trading Company were experienced, now there is firm commitment to ensure that fast tracked deliverables are forthcoming; * Targeted support to key economic sectors: department of economic development is working with JICBC to establish working forums in targeted economic subsectors - on track; * Extension for the urban development zone incentive has been granted by the national Treasury for a further five years; and * Better Buildings - reconfigured programme now due June 2008. Feasibility studies, financial modelling and legal advice on structuring currently being undertaken.
Community development
Summary of progress * Database of 100 crèches was compiled and measurable support given, three service providers appointed to provide mobile early childhood development capacity building of crèches, and 28 practitioners trained to date; * Options for application of the social package are currently being investigated, together with revised tariff issues; * Excellent progress on all non-time dated programmes; and * Developing norms and standards policy for sports and recreation facilities, but finalisation outstanding as it needs more explicit focus in light of proposed residential densification.
Transportation
Summary of progress * The updated Saturn traffic model for the inner city is complete. This is the first time in the history of the city that a morning and afternoon peak model is available for traffic flows in the inner city. Johannesburg Development Agency on site with phase one of BRT in the inner city; * Comprehensive solution to on and off street parking progressing; * Special commitment to CBD congestion points has been made; * Public environment upgrade has taken traffic and pedestrian safety concerns into consideration; and * Roll out of ward safety planning started January 2008.
Residential development
Summary of progress * Transitional housing - although delayed: MBV (317 beds) and Old Perm (150 beds) complete except for final delivery of beds. 228 units completed in BJ Alexander. Chelsea Hotel also in process (155 units), and other buildings (Rosabel Place, Vannin Court, MBV phase two and Casa Mia) have started; and * R3-million from the original capital allocation for temporary accommodation in Hospital Hill building redirected to community development department for refurbishment as a street children sanctuary.
Key commitments * Sustained urban management; * Public environment upgrade - Hillbrow, Berea and Yeoville and planning of next year's capital allocation; * Coherent city improvement district and neighbourhood improvement district programme of support to three initiatives; * Housing action plan; * Innovative bad buildings approach; * Sectional title support; * Reconfigured Better Buildings Programme launched; * Informal trading and linear markets; and * Also the urgent need for enhanced communication.
Summation * 43 time dated deliverables due by December 31, 2007:
* Most of the rest of 2007-08's commitments under way. A minority likely to not be achieved at all (for example, University of the Witwatersrand, education campus sports facility shared-usage agreement; clearance certificate issues; roll-out of broadband as "partner" will only be selected at the end of May). During the next week I hope to have time to interrogate the report and will bring you my comments next week. Regards, Neil Related stories: |